Gas Plant Survey Work Experience

BHP Zamazma Gas plant

Execution survey for ACL project of BHP Zamzama Gas plant in March 2001 to till August, 2001 at Dadu.

Responsibilities

Executed the plant design as per drawings and controlled the distance, angles and levels given on drawing. In this project, we completed the 3.2 kilometer road earth work including 7 numbers of pipe culverts.

Horizontal & Vertical Control of

  • Equipment’s foundations
  • Pipe racks foundations
  • Evaporation pond earth work
  • Wellhead foundation
  • Pipe Culverts
  • Road earth work
  • Buildings
  • Tanks foundations

Sawan Gas plant

Execution survey for ACL project of Sawan Gas Field development project, including Airstrip and Gas processing plant, the airstrip length is 1665 meter, paved runway 30 meter width, shoulders 60 meter on each side, Taxiway, Apron, Parking. From February 2002 to September 2002 at Khairpur district.

Responsibilities

Executed the plant/runway design as per drawings and controlled the distance, angles and levels given on the drawing. In this project, Xpert Surveyors completed the Airstrip including shoulders, taxi way, apron, parking & Gas processing plant.

Horizontal & Vertical Control of

  • Equipment’s foundations
  • Pipe racks foundations
  • Runway earth work
  • Sub base & Base course
  • Site Roads earth work
  • Buildings of permanent camp
  • Tanks foundation
  • Earthen embankments